Public Notice - New Sidewalk Construction - Cherry Street (Frontier Drive to Henry Street)

WHAT: The Town of Niagara-on-the-Lake, through its contractor Niagara Concrete Forming and Finishing, will commence with the construction of a new 1.8 metre curb-face sidewalk along the south side of Cherry Street, from Frontier Drive to Henry Street. 

WHEN: Sidewalk construction is planned to commence Monday, July 21, 2025, with the full construction and restoration expected to take approximately two weeks to complete. 

CONTACT: Robert Alguire, Engineering Technologist, Town of Niagara-on-the-Lake at robert.alguire@notl.com or 905-468-3266 ext. 283.

COMMUNICATION: Information regarding this project will be posted on the Town’s website and social media accounts. Affected residents have been notified of the scheduled construction and will be communicated with throughout the length of the project. 

Thank you for your patience and cooperation.